Hyde Park School Energy Conservation Project |
Cincinnati Public Schools Hyde Park Work Items: – Geothermal HVAC System – HVAC Control System – Modified Secured Entrance – Elevator serving Basement to Third Floor – Asphalt Paving Geothermal Area – Gymnasium Lighting – Window – Voice/Data Infrastructure – Exterior Doors – Technology – Suspended Ceiling – Security – Upgrade Electrical Service – Domestic Hot Water Heater – Lighting Fixtures & Occupancy Sensors Total Budget: $5,521,674.00 Projected Time Line: July 12 – CPS move August 12 – Design Complete September 12 – Buyout October 12 thru November 13 – Hyde Park Phase I & Well Field December 13 – CPS move January 14 thru July 14 – Hyde Park Phase II August 14 – CPS move |